The Wireless Network Upgrade Project officially ended June 30th, 2021 and any remaining deployments are to be considered part of regular operations. There are 22 buildings remaining in various stages of readiness: 1 waiting on …
Wireless Upgrade
Campus Wireless Upgrade, May 2021 Progress Report
May was a major push for AP deployments, switch review and building cutovers. 1281 AP’s were deployed or cutover during this month, with new deployments at 8 buildings. The infrastructure team has completed all wiring …
Campus Wireless Upgrade, Apr 2021 Progress Report
April was another productive month for this project. The infrastructure team is finishing up the final building (Memorial Library) and is targeted to be completed early this month, which will conclude the infrastructure involvement of …
Campus Wireless Upgrade, Mar 2021 Progress Report
The month of March saw the Field Services team deploy 625 AP’s at 9 buildings. Alongside the AP deployments, the Field Services team has continued to fully cut-over buildings, which is the final step after …
Campus Wireless Upgrade, Feb 2021 Progress Report
The month of February saw 1248 AP’s deployed at 16 buildings. AP unboxing and configuration was completed in February by the Field Services team and they are now working on deployments as well as patching …
Campus Wireless Upgrade, Jan 2021 Progress Report
As we ramp back up after the new year, we are continuing unboxing of the large AP order that arrived at the end of the year, and prepping the AP’s for Westphal to continue their …
Campus wireless upgrade, Dec 2020 progress report
Another month of great progress for AP deployments. Despite the short month with holiday outages, December was a continuation of the strong November with the Field Service team working on AP unboxings and configurations and …
Campus wireless upgrade, Nov 2020 progress report
We have continued a concentrated push for AP deployments this month, with Westphal leading the deployment of new AP’s and the Field Services team doing the unboxing and configuring of the new AP’s. We had …
Campus wireless upgrade, Oct 2020 progress report
October was dedicated to AP prep work from Field Services as they prepared for Westphal’s involvement in new AP deployments. All newly ordered AP’s have been delivered and Field Services continues to work on unboxing …
Campus wireless upgrade, Sept 2020 progress report
September was a month largely dedicated to validation of switches and prep for building AP deployment. While it was initially planned that there would be a big push on 3 of the larger buildings, some …