Campus wireless upgrade, April 2020 progress report

The Field Services team has fully restarted the delivery of designs to make sure that Westphal continues to have work. They have delivered 8 new designs this month, after working to get back on campus and begin some of their normal work. The expectation at this point is to target the delivery of all designs by the end of June, which is 2 months off the original expectation. There are 27 designs left to be delivered for wiring. At that point, the project will shift to focus completely on the install of AP’s on all buildings. I believe that, given the delay due to COVID and the transition we will be looking at from designs to AP installation, it is important that the entire project team meet to discuss the next steps, timeline, expectations and project delivery.

April 2020 UW Wireless Upgrade Status Report [PDF]

TOTAL ACCESS POINTS INSTALLED:
3163 OUT OF 6792 = 47% INSTALLED