Campus Wireless Upgrade, Jan 2021 Progress Report

As we ramp back up after the new year, we are continuing unboxing of the large AP order that arrived at the end of the year, and prepping the AP’s for Westphal to continue their progress of AP installs. There was a dip in New AP deployments do to ramping back up and unboxing efforts of AP stock but 4 buildings were finished for a total of 356 new AP’s, and there are 8 buildings in progress for another 779 new AP’s that are expected to finish in the next week or two. The Field Services team is continuing to make their way through the buildings after Westphal to do building reviews and finalize building prep for AP transitions. Infrastructure continues to make great progress on wiring with only a few more large buildings left for wiring.

January 2021 Wireless Upgrade Progress Report [PDF]

TOTAL AMOUNT OF APs INSTALLED
6684 OUT OF 12104 = 57% INSTALLED