Campus wireless upgrade, July 2020 progress report

The Field Services team has delivered all building designs and begun the deployment of the AP’s at the most important buildings identified. They have finished one building for 77 AP’s deployed at the end of July. They are focusing on lab and communal spaces and the larger classrooms that may be operational when school reopens in the fall. Field Services has prepped, and is scheduling, 33 buildings for AP deployment with the expectation that they will make a good push for deployment progress over the next couple of months with all the prep work that has been done. The electric shop and Westphal continue to make great progress finalizing the wiring for the final handful of buildings.

July 2020 UW Wireless Upgrade Status Report [PDF]

TOTAL AMOUNT OF AP’S INSTALLED
3240 OUT OF 6792 = 48% INSTALLED