Campus wireless upgrade, June 2020 progress report

The month of June was dedicated to finishing building design work and planning for the start of concentrated AP deployment by identifying the most important buildings that need to be accomplished before the fall semester starts. At Jeanne’s direction the Field Services team is working to identifying the common spaces and labs that will likely be the most occupied when school resumes. Westphal and Electric Shop are working to complete the wiring of the remaining designs submitted. The major focus going forward for Field Services will be on planning and deployment of APs in the critical areas identified.

June 2020 UW Wireless Upgrade Status Report [PDF]

TOTAL AMOUNT OF ACCESS POINTS INSTALLED
3629 out of 6792 = 53% INSTALLED