The month of February saw 1248 AP’s deployed at 16 buildings. AP unboxing and configuration was completed in February by the Field Services team and they are now working on deployments as well as patching and cut overs of buildings with all AP’s installed. Field Services is also assisting with the switch review and count to ensure we have enough switches and provide order information to Dennis, as necessary. The Electric Shop is continuing their progress of wiring in the 5 remaining buildings with a still expected completion date of the end of May.
February 2021 Wireless Upgrade Progress Report [PDF]
TOTAL AMOUNT OF APs INSTALLED
8232 OUT OF 12104 = 68% INSTALLED