Campus Wireless Upgrade, Apr 2021 Progress Report

April was another productive month for this project. The infrastructure team is finishing up the final building (Memorial Library) and is targeted to be completed early this month, which will conclude the infrastructure involvement of this project. That will leave the AP installations for Field Services as the remaining items as we move towards the project wrap-up date of June 30th. Field Services completed installing AP’s at 5 buildings for a total of 499 AP’s. They are also continuing to cutover buildings, do the final inspections, and otherwise ensure completion. At this point, they have all the AP’s and switches necessary to complete this project and believe we are on track for the completion date of June 30th, if nothing abnormal derails the continued progress.

April 2021 UW Wireless Upgrade Status Report [PDF]

TOTAL AMOUNT OF APs INSTALLED
9356 OUT OF 12104 = 79% INSTALLED