Campus wireless upgrade, August 2020 progress report

We have continued AP deployments in planned buildings, deploying 347 APs and completing four buildings in the month of August. This notes the highest total of AP deployments that we have been able to accomplish since the start of this project. The Field Services team is planning on three large buildings for a total of 427 APs for the month of September. Electric Shop and Westphal continue to move through the remaining buildings for wiring and walkthroughs, with expectations that most of the buildings will be complete in the month of September, with only a few buildings remaining to be completed in early October. The biggest issues right now is the return to campus for students and faculty, and the concern that creates for some people regarding our ability to enter buildings and complete the deployment and wiring work.

August 2020 UW Wireless Upgrade Status Report [PDF]

TOTAL AMOUNT OF APs INSTALLED
3587 OUT OF 6792 = 53% INSTALLED