Campus wireless upgrade, February 2020 progress report

February was another month of more deliberate design activity. We made substantial progress in that regard, getting out another fifteen building designs. After our bi-weekly calls with Westphal/Field Services/Electric shop, we have identified a need for design to be delivered for mid-sized buildings to ensure Westphal is properly utilized. At this time, there are 54 smaller buildings and 13 larger buildings that need designs. We are working together to identify the medium-sized buildings that should have a focus on cabling. The focus on design has moved the project along quickly towards getting the buildings ready for AP install focus sometime in April/May, as planned.

February 2020 Wireless Upgrade Status Report [PDF]

TOTAL AMOUNT OF ACCESS POINTS INSTALLED
3163 out of 6792 = 47% INSTALLED