Campus Wireless Upgrade, Mar 2021 Progress Report

The month of March saw the Field Services team deploy 625 AP’s at 9 buildings. Alongside the AP deployments, the Field Services team has continued to fully cut-over buildings, which is the final step after AP’s are deployed. The infrastructure team remains on track for finishing the final buildings (Whimer, Microbial, Memorial, Ingraham) by the end of May, with MSE being available to the Field Services team for AP deployment this week. Additional switches have been ordered and are being installed as necessary in the buildings, though more switches may be necessary as Field Services continues to inventory the remaining need. Overall, we continue to make consistent progress towards the expected completion date with no major roadblocks at this point.

March 2021 UW Wireless Upgrade Status Report [PDF]

TOTAL AMOUNT OF APs INSTALLED
8857 OUT OF 12104 = 73% INSTALLED