Campus wireless upgrade, May 2020 progress report

We held a project group meeting on May 27th to realign expectations and reset our planning after the delays caused by the COVID Safer at Home orders and campus closures. We are back to mostly full speed as we target the end of June for the delivery of all buildings designs. After the building designs are delivered, we will be moving into AP installation, focusing on lab and common spaces, as classrooms will be lowest priority given there will be no fall classes. We need to provide a detailed deployment plan to give to Dennis so that he has the information to take to the budgetary committees to ensure we can purchase more AP’s in a timely manner for our plan. Gary is working with his team to create that plan as we approach AP deployment phase.

May 2020 UW Wireless Upgrade Status Report [PDF]

TOTAL AMOUNT OF ACCESS POINTS INSTALLED
3163 out of 6792 = 47% INSTALLED