Campus Wireless Upgrade, October 2021 Progress Report

The Wireless Network Upgrade Project officially ended June 30th, 2021 and any remaining deployments are to be considered part of regular operations.

There are 22 buildings remaining in various stages of readiness:

  • 1 waiting on construction
  • 5 reviewing switches
  • 3 ready to prepare access points
  • 13 ready to schedule

We are focusing our attention on the Memorial Library, Vilas Hall, GenBio, WIMR and HSLC, all of which are larger installations. The remaining smaller installations will be done as filler between the larger buildings.

TOTAL AMOUNT OF APs INSTALLED
11,810 OUT OF 11,810 = 100% DEPLOYED