Campus wireless upgrade, Sept 2020 progress report

September was a month largely dedicated to validation of switches and prep for building AP deployment. While it was initially planned that there would be a big push on 3 of the larger buildings, some issues over appropriate power needs at these locations was discovered. The team shifted its focus to two smaller buildings and prep work for the arrival of the large AP order coming in mid-October. The Field Services team were able to complete 2 buildings, for 122 AP’s deployed this month, along with the validation and preparation work. Electric Shop and Westphal continue to move through the final buildings wiring with only 16 left. There are also ongoing discussion with the Westphal team to assist with new AP deployments that could significantly ramp up the AP deployments of this project.

September 2020 UW Wireless Upgrade Status Report [PDF]

TOTAL AMOUNT OF APs INSTALLED
3709 OUT OF 6792 = 55% INSTALLED